Whakatane District

Matata Regeneration Project

Project 6. Waitepuru Swale

Project 6 schedule

Task Name Duration Start Finish
Project 6. Waitepuru Debris Control Works 370 days Mar 20 '06 Sep 18 '07
(WPD) Landowner consultation 60 days Mar 20 '06 Jun 15 '06
(WPD) Survey 10 days Jun 16 '06 Jun 29 '06
(WPD) Geotechnical Investigation 15 days Jun 16 '06 Jul 6 '06
(WPD) Confirmation of Concept/Preliminary Design 10 days Jul 7 '06 Jul 20 '06
Consents Process 130 days Jul 21 '06 Feb 7 '07
(WPD) Application and AEE 30 days Aug 4 '06 Sep 14 '06
(WPD) Third party Consultation 120 days Jul 21 '06 Jan 23 '07
(WPD) Processing 40 days Nov 27 '06 Feb 7 '07
(WPD) Consents Granted 0 days Feb 7 '07 Feb 7 '07
Design 25 days Feb 8 '07 Mar 14 '07
(WPD) Detailed Design 20 days Feb 8 '07 Mar 7 '07
(WPD) Tender Documents 10 days Mar 1 '07 Mar 14 '07
Tender Process 30 days Mar 15 '07 Apr 30 '07
(WPD) Construction 90 days May 15 '07 Sep 18 '07

Project 6 Schedule - Launch a pdf version.