| Task Name |
Duration |
Start |
Finish |
| Project 6. Waitepuru Debris Control Works |
370 days |
Mar 20 '06 |
Sep 18 '07 |
| (WPD) Landowner consultation |
60 days |
Mar 20 '06 |
Jun 15 '06 |
| (WPD) Survey |
10 days |
Jun 16 '06 |
Jun 29 '06 |
| (WPD) Geotechnical Investigation |
15 days |
Jun 16 '06 |
Jul 6 '06 |
| (WPD) Confirmation of Concept/Preliminary Design |
10 days |
Jul 7 '06 |
Jul 20 '06 |
| Consents Process |
130 days |
Jul 21 '06 |
Feb 7 '07 |
| (WPD) Application and AEE |
30 days |
Aug 4 '06 |
Sep 14 '06 |
| (WPD) Third party Consultation |
120 days |
Jul 21 '06 |
Jan 23 '07 |
| (WPD) Processing |
40 days |
Nov 27 '06 |
Feb 7 '07 |
| (WPD) Consents Granted |
0 days |
Feb 7 '07 |
Feb 7 '07 |
| Design |
25 days |
Feb 8 '07 |
Mar 14 '07 |
| (WPD) Detailed Design |
20 days |
Feb 8 '07 |
Mar 7 '07 |
| (WPD) Tender Documents |
10 days |
Mar 1 '07 |
Mar 14 '07 |
| Tender Process |
30 days |
Mar 15 '07 |
Apr 30 '07 |
| (WPD) Construction |
90 days |
May 15 '07 |
Sep 18 '07 |