Project 5. Waitepuru Bunding and Stream Works
Project 5 schedule
Resource consent decision has been appealed to the Environmental Court, physical works will be delayed until the outcome of the appeal is known.
| Task Name | Duration | Start | Finish |
|---|---|---|---|
| Investigation - completed by the end of April 2008 | Completed | ||
| Consultation/ Resource Consent Application - end of May 2008 | Completed | ||
| Consent Process | Aug '08 | ||
| Tender Construction - commence September 2008 | Sept '08 |