Project 5. Waitepuru Bunding and Stream Works
Frequently Asked Questions
That the Matata Residents Association made submissions relating to the cleaning of all streams which were not actioned.
Even if the steams were in pristine condition, unfortunately the level and significance of the May 2005 event would have seen these streams flooded and compromised.
As part of the resource consent process there is an opportunity to make “conditions” to resource consents. It is expected these conditions will include assessments and maintenance programmes to ensure stream integrity is kept intact.
Following perennial lobbying from Matata Residents and Ratepayers Assn., WDC commissioned a report on Matata Stormwater – Stream Investigation in June of 1999. This report documented the “URGENT WORKS” required and the steps necessary for its implementation. The result: inaction. The report shelved – no steam or waterway maintenance undertaken, wasting time, effort and ratepayers’ money – leaving the problems to escalate. Had that work been done, there may have been significantly less damage to Matata properties and homes on 18 May 2005.
Even if the streams were in pristine condition, unfortunately the level and significance of the event in May 2005 would have seen these steams flooded and compromised. The damage to Matata happened in a very short space of time – the steams capacity would have been breached irrespective of the report described above. This is the reason to ensure there is only a Q5 return period flow to be returned through Matata in the Waitepuru Stream. Waimea Stream is being upgraded to suit revised hydrological design flows.
Maintenance contracts will be enforced to ensure that the efforts in restoration do not get destroyed. Contract reviews will be conducted to ensure the high standard expected is maintained.
Would the WDC accept responsibility for co-ordinating the provision of storm water run-off and stream maintenance on behalf of the residents of Matata?
Part of the Resource Consent process covers future maintenance. Discussions will be held with both parties (WDC and EBOP) to ensure there are clear responsibilities for the steams in Matata.
When will the regular flow of the Waitepuru Stream be restored to its original stream bed and also therefore re-directed back into the Eastern Lagoon with the extreme flow over land to the Tarawera River?
After consultation with the affected parties – the project plan is to return this mid to late 2007. This is the first priority for the Matata Regeneration Project.
What monitoring and maintenance measures can the Community count on from WDC? The Community needs a transparent maintenance programme which the Community can monitor.
Agreed – see Resource Consent ‘Conditions’ – this will outline the expectations of the authorities in maintaining these streams.
Will WDC or one of their agents accept responsibility for clearing away items/materials capable of forming a blockage in storm conditions?
Per above – Resource Consent ‘Conditions’ – this will outline the expectations of the authorities in maintaining these streams. WDC will be one of the authorities maintaining these assets.
View other community questions with a focus on general issues.
