Whakatane District

Matata Regeneration Project

Project 4. Waimea Stream

Project 4 schedule

Task Name Duration Start Finish
Project 4. Waimea Stream Works 260 days Jun 6 '06 Jun 28 '07
(WMS) Landowner consultation 30 days Jun 6 '06 Jul 17 '06
(WMS) Confirmation of Concept/Preliminary Design 30 days Jul 18 '06 Aug 28 '06
(WMS) Survey 10 days Aug 29 '06 Sep 11 '06
(WMS) Geotechnical Investigation 10 days Aug 29 '06 Sep 11 '06
Consents Process 70 days Aug 29 '06 Dec 5 '06
Design 20 days Dec 6 '06 Jan 18 '07
(WMS) Detailed Design 20 days Dec 6 '06 Jan 18 '07
(WMS) Tender Documents 10 days Dec 20 '06 Jan 18 '07
Tender Process 30 days Jan 19 '07 Mar 2 '07
(WMS) Construction 80 days Mar 5 '07 Jun 28 '07

Project 4 Schedule - Launch a pdf version.

Project 4a schedule

Task Name Duration Start Finish
Project 4a. Waimea Debris Control 30 days Aug 29 '06 Oct 9 '06
(WMD) Geotechnical Investigation 10 days Aug 29 '06 Sep 11 '06
(WMD) Debris Control Processes and Risk 30 days Aug 29 '06 Oct 9 '06

Project 4a Schedule - Launch a pdf version.