Whakatane District

Matata Regeneration Project

Project 2. Awatarariki Dam

Project 2 schedule

Timeline

Investigation – completed by end of December 2007

Consultation/Resource consent application – completed by end of January 2008

Public notified Resource consent process – completed by end of end of June 2008

Construction – completed by December 2008