| Task Name |
Duration |
Start |
Finish |
| Project 1. Ohinekoao Stream Works |
215 days |
May 11 '06 |
Mar 28 '07 |
| (OHK) Liaison Planning OnTrack and Transit |
30 days |
May 11 '06 |
Jun 22 '06 |
| (OHK) Survey |
10 days |
Jun 23 '06 |
Jul 6 '06 |
| (OHK) Geotechnical Investigation |
15 days |
Jun 23 '06 |
Jul 13 '06 |
| Confirmation of Concept/Preliminary Design |
20 days |
Jul 7 '06 |
Aug 3 '06 |
| Consents Process |
30 days |
Aug 4 '06 |
Sep 14 '06 |
| Design |
15 days |
Sep 15 '06 |
Oct 5 '06 |
| OnTrack and Transit Consents and Design Process |
120 days |
Jun 23 '06 |
Dec 8 '06 |
| Tender Process |
15 days |
Dec 11 '06 |
Jan 16 '07 |
| (OHK) Construction |
50 days |
Jan 17 '07 |
Mar 28 '07 |