Whakatane District

Matata Regeneration Project

Project 1. Ohinekoao

Preliminary Consultation & General Design Criteria Review and Confirmation

Task Name Duration Start Finish
Investigation - completed by the end April     Completed
Consultation/ Resource consent application     Completed
Consent Process - end of July 2008     July '08
Tender Construction   August '08  

Project 1 schedule

Task Name Duration Start Finish
Project 1. Ohinekoao Stream Works 215 days May 11 '06 Mar 28 '07
(OHK) Liaison Planning OnTrack and Transit 30 days May 11 '06 Jun 22 '06
(OHK) Survey 10 days Jun 23 '06 Jul 6 '06
(OHK) Geotechnical Investigation 15 days Jun 23 '06 Jul 13 '06
Confirmation of Concept/Preliminary Design 20 days Jul 7 '06 Aug 3 '06
Consents Process 30 days Aug 4 '06 Sep 14 '06
Design 15 days Sep 15 '06 Oct 5 '06
OnTrack and Transit Consents and Design Process 120 days Jun 23 '06 Dec 8 '06
Tender Process 15 days Dec 11 '06 Jan 16 '07
(OHK) Construction 50 days Jan 17 '07 Mar 28 '07